Offshore (Kizomba B – FPSO Angola) Puesta en marcha de generador de emergencia
SCOPE OF WORK
Electrical tests
- Insulation resistance, polarization index and dielectric absorption ratio of:
- Stator winding.
- Rotor winding.
- Main exciter stator winding.
- PMG stator winding.
Inspection and verifications
- Electrical connections of three phase rotating rectifier bridge.
- Connections of main exciter, PMG and rotor winding.
- RTDs, thermocouples, current transformers, and space heaters.
- Generator foot shims and clamp.
- Cleaning of main terminals and generator cables.
- Cleaning of the generator compartment and connection box.
Heat run commissioning tests
- Bearings temperatures.
- Windings temperatures.
- Air flow temperatures.
- Bearing vibration levels.
- Voltage and current balance.
Categoría
TFA, Turbo generator
Etiquetas
Minor Inspection, Offshore, TFA, Turbo Generators