Offshore (Kizomba B – FPSO Angola) Puesta en marcha de generador de emergencia

SCOPE OF WORK

Electrical tests

  • Insulation resistance, polarization index and dielectric absorption ratio of:
  • Stator winding.
  • Rotor winding.
  • Main exciter stator winding.
  • PMG stator winding.

Inspection and verifications

  • Electrical connections of three phase rotating rectifier bridge.
  • Connections of main exciter, PMG and rotor winding.
  • RTDs, thermocouples, current transformers, and space heaters.
  • Generator foot shims and clamp.
  • Cleaning of main terminals and generator cables.
  • Cleaning of the generator compartment and connection box.

Heat run commissioning tests

  • Bearings temperatures.
  • Windings temperatures.
  • Air flow temperatures.
  • Bearing vibration levels.
  • Voltage and current balance.
Categoría

TFA, Turbo generator

Etiquetas
Minor Inspection, Offshore, TFA, Turbo Generators